OD & RD Equal Zero When Converting from P6 to P3 (????)
In the Open Standard
Benjamin MoraMember for 19 years
- Created
- 2
- 2
0
My issue is that when I am using P6 and converting to P3 the OD & RD become zero in the P3 version of the schedule.
Here are my settings:
-All tasks = physical % Complete
-Drive Activities Dates by Default = unchecked
-Duration Type = Fixed Duration & Units\Time
-All units are zeroed out
-Recalculate Actual Units & Cost when Duration % complete changes = unchecked
-Link Budget & At Completion for not Started Activities = Checked
-Reset Remaining Duration & Units to Original = Checked.
-All activities = Task Dependent.
By the way, this schedule was originally a conversion from P3 that went to P6 and is now going back to P3.
Any clues?
Here are my settings:
-All tasks = physical % Complete
-Drive Activities Dates by Default = unchecked
-Duration Type = Fixed Duration & Units\Time
-All units are zeroed out
-Recalculate Actual Units & Cost when Duration % complete changes = unchecked
-Link Budget & At Completion for not Started Activities = Checked
-Reset Remaining Duration & Units to Original = Checked.
-All activities = Task Dependent.
By the way, this schedule was originally a conversion from P3 that went to P6 and is now going back to P3.
Any clues?
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?