Splitting / Necking in P6

Athar HashmiMember for 17 years 6 months
Created
3
2
0
Dear Freinds

Please help me to show the necking in bars in P6. How can I show splitted activity. I already marked check boxes ’calendar non-working time/activity non work intervals’, but necking is not appearing in bars.

3 replies

Oldest first
  1. 0
    Neal Walsh ·
    Athar,

    By splitting, do you mean you want to stop an Activity on a certain date then commence at a later date? Or do you purely just want to ’neck’ or sausage the bars as I call em?
    By right clicking the Gantt Chart / Bars / Bar Settings and then by checking the calendar non-work time box ( dont forget you have to do this for every bar you want to be necked) then this should work.....

    Walshy
  2. 0
    Athar Hashmi ·
    Thanx Neil, it’s working now.
    (I wasn’t doing this (necking) for every bar.)
  3. 0
    Neal Walsh ·
    No probs Athar, glad you have it sorted now ;)

    Walshy