Activity Usage Profile -A Query
In the Open Standard
Gary WhiteheadMember for 17 years 6 months
- Created
- 4
- 5
0
I’m looking for a way to display the Activity Usage Cumulative profile, but starting from the data date rather than the project start date. -ie All cumulative values would be zero at data data.
Can this be done? There’s an option to ’display activities for selected time period’, but I can’t work out how to select the time period!
Any help much appreciated.
Cheers,
G
Can this be done? There’s an option to ’display activities for selected time period’, but I can’t work out how to select the time period!
Any help much appreciated.
Cheers,
G