Progressing and resource loaded activity

Brian MittonMember for 18 years 7 months
Created
1
1
0
G’day folks,

Your assistence please.

I have loaded an activity with a quantity.

When I progress this activity and insert the actual quantity, I store the performance. On this occasion I am reducing the remaining duration. So when I do this, the actual quantity increases????

How do I fix the actuals and still change the remaing duration?

Thanks.

Brian

1 reply

Oldest first
  1. 0
    David Kelly ·
    Brian,

    In P6, reducing remaining duration means that you are increasing the "Duration % complete"

    So, the easy (!?) answer is that "Recalculate actual units and costs when duration % complete changes" is ticked in the "Calculations" tab at the project level.......