Progress On baseline

Izam ZakariaMember for 20 years 4 months
Created
3
2
0
Gents,

Anyone know how to do this? do the progress bar on baseline bar.

3 replies

Oldest first
  1. 0
    David Kelly ·
    Yes but......

    Shading in baseline bars with progress is just deflection activity to disguise that fact that no earned value analysis is being done.

    That’s today’s lecture over!

    You need to run a global change


    user_number1=BL Project Duration*Activity % Complete
    And user_number1=user_number1/100.00
    And user_number1=user_number1/8.00
    And user_end_date=BL Project Start+user_number1
    And user_start_date1=BL Project Start

    Note the figure 8 is the number of hours in a day. The aboce global change needs repeated for each calander if you have calendars with different working hours.

    Now you draw a user bar from start1 to end.....
  2. 0
    Izam Zakaria ·

    You are the man. I will execute this rapidly.
  3. 0
    Izam Zakaria ·
    Hi Kelly

    I tried already and it’s works man.

    You are the original dude.