Skip to content

Group Totals not matching duration

Scott McCarthy-PunzanoMember for 19 years 8 months
Created
3
2
0
I’m having real difficulties with this.

For example, I have 5 activities in a group, the total duration from start to finish is 10 days and one hour, yet the Group Total shows 4days and 4 hours??

I have all the activities on the same calander....

??

HELP!

Cheers,
Scott.

3 replies

Oldest first
  1. 0
    Muhammad Anwar ·
    Scott,

    The Duration in Group band(summary duration) is calculated from Global default calendar and unit of time admin preference(ie 8h/d or 10/d). It starts from the earliest time in the group of activities. If hrs/day in user preference and default duration in admin preference are same as well as default Global calendar is same as activities calendar then you should not experience this problem.

    regards

    M
  2. 0
    Muhammad Anwar ·
    Scott,

    The Duration in Group band(summary duration) is calculated from Global default calendar and unit of time admin preference(ie 8h/d or 10/d). It starts from the earliest time in the group of activities. If hrs/day in user preference and default duration in admin preference are same as well as default Global calendar is same as activities calendar then you should not experience this problem.

    regards

    M
  3. 0
    Scott McCarthy-Punzano ·
    Thanks Muhammad!

    Great fix!

    Scott.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?