WBS- SUMMARY DURATION

Alaa Al hajMember for 18 years 11 months
Created
7
1
0
HI
EID MUBARAK TO ALL
does anybody know how primavera 6 calculate original duration for WBS- level when organizing activities by WBS
cause i have 12 W/ H calendar but primavera consider as 20 hours when calculating duration for wbs level
i don’t know why

yours
Alaa

7 replies

Oldest first
  1. 0
    Anoon Iimos ·
    please check your global calendar
  2. 0
    A D ·
    at summary level, P6 uses global calendat to calculate duration.

    Global calendar and project calendar need to be same to show matching figures
  3. 0
    Arnold Puy ·
    Hi Alaa,

    Try to use WBS Summary as activity type for each WBS level or to the highest level.

    With P6 v7, each calendar has its own "Time Periods" so you don’t have to worry.

    Regards,

    Arnold
  4. 0
    Neal Walsh ·
    Alaa,

    This has always been an issue with P6, upto 6.2, and as Arniold states, v7 has its own time periods to correct this problem.
    However, on versions prior to this, set your durations to hours and the issue will be resolved.

    Regards,

    Walshy
  5. 0
    Neal Walsh ·
    *Arnold

    Sorry Arnie! :-)

  6. 0
    Arnold Puy ·
    Hi Neil,

    You are right..

    It’s okey..

    Regards,

    Arnold
  7. 0
    Alaa Al haj ·

    Thanks All
    i change the default Global Calendar to match the project Calendar
    and now it is ok
    i don’t know what will we do without the best planner around the world on this Forum

    thanks again
    we should be proud of this Forum


    yours
    Alaa

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?