Updating Level-of-Effort Activities

Ashish AbrahamMember for 19 years 10 months
Created
2
1
0
Hello,

I am currently working on a P6 schedule with several cost loaded level-of-effort activities. Is it possible to update such activities...I mean, can I change the percent complete on these activities?

Please advise.

Thanks!

2 replies

Oldest first
  1. 0
    Anoon Iimos ·
    set percent complete type to physical and change it
  2. 0
    Neal Walsh ·
    And you’re in Forensic Claims? hmmmmmm......

    Anyway, the LOE Activities act as a Hammock to the group it is spread across, and if you have assigned the LOE correctly (SS,FF) then your % complete will increase in relation to the Activities. You have to manually update your cost of work done allocated to these though.