"Reorganize Now (Shift+F2)" command in tools menu is disabled. Why?

how can we enable it?

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Sajid,

    Go to Edit --> User Preferences --> Application tab, under Group and Sorting, untick the "Reorganize Automatically".

    Regards,

    Arnold
  2. 0
    Sajid Syed ·
    Done

    Million Thanks.

    Shifting to p6 from p3 is an uphill task. the slope would have been much steeper without help from friends like your self.


    Regards
  3. 0
    Arnold Puy ·

    You are welcome Mr. Sajid.