activities IDS

Sherif SaiedMember for 16 years 11 months
Created
2
1
0
HI GUYS , CAN I CONTROL THE INCREMENT OF THE ID LEN EXGTH COZ I NEED TO MAKE EACH UNIT NOT UNIQUE IN ITS ID EXCEPT IN ITS PREFIX ONLY,,,

2 replies

Oldest first
  1. 0
    Alaa Al haj ·
    HI SHEREF

    IN P6 MAXIMUN id LENGHT IS 20 characters LIKE ABCDEFGHI1234567899
    BUT IN P3 MAXIMUN IS 10 ABCDEFGHI

    YOURS
    ALAA
  2. 0
    Arnold Puy ·
    Hi Sherif,

    Welcome to Planning Planet.

    What do you want to limit the Length or the Increment?

    If the Length, go to Admin --> Admin Preferences --> ID Lengths tab --> Activity ID maximum characters.

    If the Increment, then go to Project Detail --> Default tab --> Auto-numbering Defaults.

    Regards,

    Arnold