Can some one tell me how to display the total for "Schedule % Complete" column


Regards

1 reply

Oldest first
  1. 0
    Arnold Puy ·
    Hi Sajid,

    You can only show your "Schedule % Complete" in the summary band if your programme is cost loaded.

    Regards,

    Arnold