Automatic Updation

Arun VasanthMember for 17 years
Created
5
3
0
Dear friends

How we can do the automatic updation for the comparison of planned progress Vs Actual progress.

With regards
Arun.V

5 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Arun,
    you will use Tools, Update Progress the same way as in P3.
    Alexandre
  2. 0
    Arun Vasanth ·
    Thnxs Alex
    Thnxs Planning planet

    Arun.V
  3. 0
    Paul Harris ·
    I strongly recommed against using Update Progress or the Apply Actuals function in P6 as these may change actual dates and unfortunately does not work exactly the same way as P3, SureTrak or MSP. This issue is all tied up with the Planned Dates which I would like to see removed from the software all toghether.

    There is a technical article on my websites titled "Issues and Solutions facing Construction Contractors Implementing Primavera P6" which explains what happens, see slide 51.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au
    www.primavera.com.au - an Oracle Primavera scheduling software resources web site
  4. 0
    Arun Vasanth ·
    thnx paul
  5. 0
    Mk Tse ·
    Paul,

    User seldom to check the display baseline bar match the original programme or not, especially if it is a large network.

    Support your finding, not recommend any in-progress or completed project to be baseline

Log in or join to reply