Primavera automaticaly inputting budegeted labour unit?

John Paul AugustineMember for 16 years 7 months
Created
13
2
0
Hi all,
I have found a problem in my primavera program. I didnt assign any labour type resources to the activities of my program. But in Budget Labour units column, Primavera is showing some values?
Why it is coming like this?
How we can fix this problem?
Can any one help me.......
Thanks in advance.......

13 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi John,
    Did you put any cost on the Activity Detail-> Status tab-> Labor Cost -> Budget field?
  2. 0
    John Paul Augustine ·
    No i didn’t input any cost in the Activity Detail-> Status tab-> Labor Cost -> Budget field..

    I already corrected by filling down the budgetted labour units to zero manually..
    But i should like to know why it is coming like this?
    is there any settings i need to change in Primavera????/
  3. 0
    Rodel Marasigan ·
    John,
    Did you create the Project or inherit/ import from someone?
  4. 0
    John Paul Augustine ·
    I am not the one who create this program.
    Actually i import it from other person...
  5. 0
    Rodel Marasigan ·
    John,
    That’s the reason why. He might do something that you are not aware of.
  6. 0
    John Paul Augustine ·
    Thank you Mr. Rodel..
    but i find the same problem with other project plan also..
    what may be possible reason for that?
  7. 0
    Rodel Marasigan ·
    John,
    If the Project was inherit or import from others you don’t have any control on what’s on the file until you manage to fix it. If the Project was newly created by you then you are aware of the history whether you did something or not.
  8. 0
    John Paul Augustine ·
    Yor are correct Mr. Rodel
    But i find in internet that this type of error is occuring in P6 commonly.
    I am pasting that link here
    http://forums.oracle.com/forums/thread.jspa?messageID=3378954
    in this link it is mentioned that
    Please
    reference Solution ID
    prim18501 in
    our Knowledgebase for anothere cause and more
    information on "No resources assigned but Budgeted
    Planned Labor units does not equal zero (0)"

    but i couldn’t access to this knowledgedata base?
    can you please check with this
  9. 0
    Rodel Marasigan ·
    Sorry John,
    The old Knowledgebase site is gone and redirecting to Oracle site. I logon and tried to find but nothing found.
    There must be some patch like SP1 & SP2 but I’m not sure. What version of P6 are you using? I have 6.1 & 6.2 and both of them don’t have problem.
  10. 0
    John Paul Augustine ·
    Thank you Mr. Rodel for your reply...\
    I am using Primavera 6.0...
  11. 0
    Godstime Mega ·

    hello everyone here , please

    hello everyone here , please i wanted to know more about  (REMAINING UNIT/TIME and AT COMPLETE UNIT) the reason i wanna know is that if  I assign 1 to my  REMAINING  UNIT/TIME , MY AT COMPLETE will automatically change to 42 , when its  remaining unit is 2 my at complete will automatically change to 84..... please  can anyone help on how to go about the calculations

    thanks

  12. 0
    Syam Mohan ·

    hello everyone,

    hello everyone,

                          I want to create generate histogram for office staff and direct labour. How it is possible.?

     

  13. 0
    Zoltan Palffy ·

    recourses can not

    recourses can not automatically assign themselves to activities so someone had to do this 