MIlestones with invalid relationships...
In the Open Standard
Bo JohnsenMember for 20 years 7 months
- Created
- 2
- 1
0
Hi,
When looking at the schedule log I get some warnings / errors concerning "milestones with invalid relationships".
When examining the milestones reported as invalid and those not reported as errors I can’t find any specific differences. What I’m looking for to correct this issue?
I tried to run a schedule check in Pertmaster/PRA on the same programme and even though also a Primavera product, Pertmaster didn’t report anything on "milestones with invalid relationships".
Any suggestions how I can sort out the "invalid milestone"-problem?
Regards,
Bo
When looking at the schedule log I get some warnings / errors concerning "milestones with invalid relationships".
When examining the milestones reported as invalid and those not reported as errors I can’t find any specific differences. What I’m looking for to correct this issue?
I tried to run a schedule check in Pertmaster/PRA on the same programme and even though also a Primavera product, Pertmaster didn’t report anything on "milestones with invalid relationships".
Any suggestions how I can sort out the "invalid milestone"-problem?
Regards,
Bo
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?