Start - Predecessor activity with a finish milestone
In the Open Standard
Richu RoseMember for 19 years 8 months
- Created
- 3
- 2
0
Hi,
I have the following problem in P6:
I have assigned activity A with a finish mile stone, finishing on 01st March 10 08:01 AM (08:01 AM is the time appearing in the finish column0 .
Activity B having a duration of 03 days with activity A as the predecessor & FS relationship shows start date as 01st March 10 08:01 AM & finsh date as 04-Mar-10 08:01 AM. Is’nt this wrong.
In fact the correct finish date for activity A must be 01st March 10 06:00 PM & for activity B start date as 02nd March 10 08:00 AM & finsh date as 04-Mar-10 06:00 PM.
How do i get this right in P6.
Cheers,
Richu
I have the following problem in P6:
I have assigned activity A with a finish mile stone, finishing on 01st March 10 08:01 AM (08:01 AM is the time appearing in the finish column0 .
Activity B having a duration of 03 days with activity A as the predecessor & FS relationship shows start date as 01st March 10 08:01 AM & finsh date as 04-Mar-10 08:01 AM. Is’nt this wrong.
In fact the correct finish date for activity A must be 01st March 10 06:00 PM & for activity B start date as 02nd March 10 08:00 AM & finsh date as 04-Mar-10 06:00 PM.
How do i get this right in P6.
Cheers,
Richu
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?