Any way to print Step activities together with main act

Abbas IndiaMember for 17 years 3 months
Created
3
2
0
Dear friends,

Anybody knows how to print Step activities together with main activities?

Awaiting for your responses.

Thanks,
abbas.

3 replies

Oldest first
  1. 0
    Wilfredo Jr. Flores ·
    Hi Abbas,



    There’s no way to print the steps activities together with the main activity, however, you can highlight the steps then copy, paste to excel then modify / add the main activity
  2. 0
    Cindy Hammack ·

    Create a reports in the

    Create a reports in the report wizard. You can add all the columns and information you want. We’re about to start using them for routing and pick sheets. One of the lesser - yet powerful - functions of P6 if you know how to use them. Also, when creating the steps use a description of each step to make it less ambiguous and provide detailed requirements for the step.