Shifting the Planned Start of Multiple projects.

Tim BreedingMember for 17 years 5 months
Created
6
5
0
Does anyone have a crafty idea how to move the Planned Start date out 1 week for many projects at the same time?

6 replies

Oldest first
  1. 0
    Dieter Wambach ·
    View "Projects" --> Modify the utmost project --> mark all you want to move --> click into the column "Planned Start" --> "Fill Down"
  2. 0
    Tim Breeding ·
    I’m talking about 1100 projects with an infinite variety of planned starts.
  3. 0
    Mike Testro ·
    Hi Tim

    In Powerproject enterprise I would select all 1100 projects - put them uner 1 summary bar and drag that top bar to the left by one week and then flag it to start then.

    I know nothing about P6 but if you can’t do that then it confirms my suspiscions - it is a crap peice of software.

    Best regards

    Mike Testro
  4. 0
    Tim Breeding ·
    What is Powerproject Enterprise?
  5. 0
    Mike Testro ·
    Hi Tim

    Go and look at astadev.com to see what Powerproject can do.

    I have been using it for the last 18 years.

    Also go and see how many problems are logged on the Asta PP thread as against the primavera threads. 100 - 1 against I would suggest.

    Vladimir and Rafael will pitch for the Russian product called Spider but i prefer to work with something that is used by most operators in the UK.

    Best regards

    Mike Testro
  6. 0
    Dieter Wambach ·
    Hi Tim

    I assume that your projects are in P6 and to hear from salesmen that other products are so much better doesn’t help you for your current task.
    1100 projects shouldn’t be a problem but please explain what you mean by variety of planned dates?

    Regards

    Dieter

Log in or join to reply