Issue importing MSPROJECT in P6 - HELP

Alvaro RigamontiMember for 19 years 11 months
Created
2
4
0
I need to import a project from MSPROEJCT2007 in P6.

When I try to lunach the importing routing from P6 ( file(import/import format/Microsoftproject/next/project/next/select file/import to EPS XXX/next/next/finish

the routin start to import trying to create a temporaty file ( process 1 of 1) and this message come out
" cannon save the project
Microsoft project does not support saving projects into ODBC, MPD or MDB formats. Please save the file in a format that is supported by project.

This is the first time i have this message

can you give me some indications

2 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·
    Alvaro,
    the fact is, you cannot have MS Project 2007 and Primavera P6 on the same machine; and therefore you cannot import a MSP2K7 into P6 or a P6 project into MSP2K7
    MSP2K7 does not recognize other file formats than MS Project, MS Project 2003, Excel and XML.
    If your project was not too large to do so, you could export the tables to MS Excel, then import the Excel tables into P6. I am not sure that this is realistic!
    Happy new year
    Alexandre
  2. 0
    A D ·
    Hi Alex,

    I have never used Primavera Project Link, but i do understand that it helps to work in a MSP enivironement when still connected with P6.

    May be u can just throw some light and guide us.

Log in or join to reply