Physical % Complete vs. Duration % Complete
In the Open Standard
Nickie LauMember for 22 years 7 months
- Created
- 5
- 2
0
Dear All,
I have just been handed a project that is already half way through, but work programme is in such a manner that updating is a nightmare.
Is it true that once we start to monitor the physical % complete, it is not possible to have the programme calculate the remaining duration without updating the duration % complete?
I appreciate any kind of suggestion. Thanks in advance.
I have just been handed a project that is already half way through, but work programme is in such a manner that updating is a nightmare.
Is it true that once we start to monitor the physical % complete, it is not possible to have the programme calculate the remaining duration without updating the duration % complete?
I appreciate any kind of suggestion. Thanks in advance.
5 replies
Oldest firstLog in or join to reply