Seeing Resource Utilisation
In the Open Standard
JS
Jay SMember for 18 years 4 months
- Created
- 9
- 3
0
9 replies
Oldest first- 0DWDieter Wambach ·You may create a report, group "Summary Resource Assignments" --> colunms: "Project" --> Group&Sort: "Resource" --> Filter: is under ... or whatever you need.
As this report will read Summary Data, all projects will be analyzed.
Don’t forget to run Tools --> summarize --> all Projects to obtain current data.
regards - 0JSJay S ·Appologies Dieter this dont seem to work it only shows open project ? Is there maybe something else I need to Know ?Step I Used
1) Tools - Summarize - All Project
2) Tools - Report Wizard - New Report Summary Resource Assignments
3) Columns It Showed activity Detail I Changed it to Project Field Only.
4) Group & Sort Change to Resource ID Name (no Ident)
It works good for the Open Report but does not look at the closed report (That is if I have a project open ?
Any Suggestion.
I Have tried running this repirt from Tracking etc.
Maybe there is something small I am not doing ?
- 0DWDieter Wambach ·@Barry
Summarized data is cumulated data. Those are special tables accessible even if a project isn’t open. How in detail is given by Admin Preferences --> Options.
@ "Plan"
I just checked again. The report works and shows each project a resource is assigned for closed projects as wewll. I didn’t check for planned and inactive.
- Do you have access to those resources (Admin --> users --> Global Access --> "All resources" marked?)
- Which filter are you using?
- Do you have access rights to the closed projects?
In addition I checked the group "Resource Assignments and replaced the filter "Open state" by the resources I wished to see. It worked as well. But be aware: For closed projects any reporting will access the summary data.
I assume, reason is the missing access right.
Good luck!
Dieter
p.s. Are you a human and have got a name? - 0JSJay S ·Thanks again Dieter still cant get it to work.
Admin Preferences --> Options.
Can you maybe be a bit more specific ?
Further
Do you have access to those resources (Admin --> users --> Global Access --> "All resources" marked?)
Yes Checked (Admin Superuser)
- Which filter are you using? (Changed it even tried resource speicif no luck it) If I remove the tik called Hide if Empty I see all the resources but not to which project they are assigned.
- Do you have access rights to the closed projects?
Could you maybe please explain a bit more ?
- 0JSJay S ·Thanks again Dieter still cant get it to work.
Admin Preferences --> Options.
Can you maybe be a bit more specific ?
Further
Do you have access to those resources (Admin --> users --> Global Access --> "All resources" marked?)
Yes Checked (Admin Superuser)
- Which filter are you using? (Changed it even tried resource speicif no luck it) If I remove the tik called Hide if Empty I see all the resources but not to which project they are assigned.
- Do you have access rights to the closed projects?
Could you maybe please explain a bit more ?
- 0DWDieter Wambach ·"Plan"
So you are "Admin Superuser". This isn’t sufficient for resource access. In addition the check box "All resources access" must be marked.
The Report:
Try a filter with equal to and use a resource where you are sure she/he is assigned to a project.
Columns: remove all items, replace by "project"
Group&Sort by resource-id name
I just checked with P6.2.1, it worked as well - before it was P6.7
Dieter - 0BCBarrie Callender ·@Dieter
I am fully aware of summarized data. I think you and I have a different interpretation of what "Plan Plan" wants. I assumed he wants to know the Activities the Resources are assigned to and I believe you are looking to just get the projects.
@Plan
It’s a pity you don’t have Primavera Web. You can make a team of your 10 or so Resources and see exactly which activities they are working on.
My laptop died this morning so can’t contribute at the moment.