Hello everyone,

How can I get % complete on summary bar, at individual activity if I am putting some % complete its does not get summarized at top level.

Thanks & Regards,

SK

3 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Kumar,

    Try to allocate cost into your activities. Your programme must be cost loaded in order to roll up the % complete in the summary band.

    Regards,

    Arnold
  2. 0
    Saurabh Kumar ·
    See Arnold,

    For Example if I update my non labor % complete in each activity, at the top summary bar I am not getting average of non labor % complete. How could I see them?

    Regards,

    Saurabh
  3. 0
    Arnold Puy ·
    Hi Saurabh,

    You mean the Nonlabor Units/Cost % Complete? Well, perhaps the reason is because, during the assignment of your resources the "Auto Compute Actuals" & "Calculate costs from units" is not tick.

    You can perform this using global change.

    Regards,

    Arnold