Primavera P6 v Power Project V11

Barney NeillMember for 17 years 8 months
Created
4
5
0
I would be intersted to hear from anyone on how these two packages compare.

Is PP V11 up to managing large Programs?

Regards

Barney Neill

4 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Barney

    Apart from the fact that you do not need a university degree in IT studies to install the software:

    Yes Asta PowerProject can accomodate very large programmes.

    One I worked on recently had 93,000 tasks and a full reschedule took less than 3 seconds - there was much more capacity available.

    Asta may be able to tell you if there is a limit but I haven’t found it yet.

    Regarding V11 I have been running it for about 3 weeks now and it is a very big step forward for user friendly interface - particularly when switching between project views.

    Best regards

    Mike Testro
  2. 0
    Barney Neill ·
    Hi Mike,

    That is very good to hear. I do remember, years ago (probably 15 actually) I had a problem with a 2000 activity programme in PP that kept falling over. At the time Asta told me that there was no limit!

    I am talking about a Program of about 200 projects, each with about 250 activities. We will never get to 93,000 activities so I feel safe. However each project will contain cost and resource data and will have a lot of coding.

    Can you tell me how big the file size for your 93,000 activity programme was?


    Best wishes,

    Barney Neill
  3. 0
    Mike Testro ·
    Hi Barney

    About 23mb

    It had cost and multiple resources.

    Look out for version 11.

    Best regards

    Mike Testro
  4. 0
    Barney Neill ·
    Thanks Mike, that will be more than enough!
    I have V11 on order.

    Barney Neill