Adding Columns in WPs & Docs + assigning Activities to

Ciamak Mir-EschghiMember for 16 years 8 months
Created
2
3
0
Hi Everybody,
1.) Does anybody know how and if at all it is possible to add columns in the WPs & Docs section. I mean other than all the columns (13) that are already available when you costumize the columns.
2.) Is it possible to import through SDK or API from an Excel file al list with all the WPs & Docs (and the information for the columns)and Activities the WPs & Docs are assigned to?
Thanks for your help!

2 replies

Oldest first
  1. 0
    Ian Nicholson ·
    You can add User Defined Fields to the WP and Docs module (Enterprise/User Defined Fields).

    I am pretty sure that the API supports access to WP and Docs. As a rule of thumb, if you can access something in the web tools (MyPrimavera), you can access it through the API.

    You could also import WP and Docs using the XER parser from the Primavera knowledgebase.

    Run, don’t walk from the SDK!
  2. 0
    Ciamak Mir-Eschghi ·
    Thanks for the info. Great help.