changing activity id from Methadology Mgt

Kumar SMember for 16 years 9 months
Created
2
15
0
Hello Guys


i am creating the project using methadology management...
i have copied the whole project to proj mgt,,

i have few related questions.....
1) can i change the activity id description (for ex 08pvc1000 to 10pvc1000) at once for all the 15000 activites. i want to chnge only the prefix of the activity id. is it possible..

2) can i copy the resources/Activity codes allocated for the previous project into this project....

3) how to break the ativity relationship..

it would be very helpful if you can clear my doubts..
thanx

2 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Satisham

    Q 1.
    I do not use P6 but if I want to make a global change to anything in Powerproject I copy paste the column into excel and then use Find - Replace to make the changes then copy it back.

    No idea at all about Q 2 & 3.

    Best regards

    Mike Testro
  2. 0
    Arnold Puy ·
    Hi Satishan,

    1. Try to use the Edit --> Replace
    2. Open the two projects and go to Activity Codes then Copy & Paste the codes.
    3. Copy the projects and in the "Copy Activity Option" untick the check box next to Relationships.

    Regards,

    Arnold