Budget Cost

Anbin PonnithMember for 17 years 4 months
Created
5
2
0
Hai
1.I did Cost Loading For my Project.I am Able to Get the Correct Budget Cost in the Activity Table .But in My Activity Usage Profile Option/Resource Usage Profile I got Difference of 60SAR(Saudi Riyal)
2.When I Import the Same Project to Another PC I got Different Budget Cost & After that if i Run Global Change (Budget Cost = Budget Material Units * Price/Unit).I am able to get the Exact Value in Activity Table & In S Curve I got Same 60 SAR Diff
How can i Fix it.
Regards
Anbin Ponnith

5 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Anbin

    Sounds like a rounding up / down error.

    Make sure that the two data sets are set to the same decimal places.

    Best regards

    Mike Testro
  2. 0
    D Artagnan ·
    Anbin,

    It’s because of the rounding up the figures. Pro’ly, the data that you imported have more than 3 decimal places but P6 can only accomodate 2 decimal places. What P6 does is round it up accordingly.
  3. 0
    Izam Zakaria ·
    Yeah i guess everybody confront the same problem. This happen too at Primavera 3. So what u need to do just play around the figure.
  4. 0
    Andrew Podolny ·
    P6 database is designed to hold up to 8 decimal points in some cases (cost_per_qty for instance is NUMERIC(21,8)) but the P6 interface allows you to see only 2 decimals.

    Regards,
    Andrew
  5. 0
    Anbin Ponnith ·
    Hai
    Thanks all for ur reply.Actually I am getting Budget unit similar to BOQ.
    My main Problem i am not able to get the Budget Cost in S Curve similar to Activity table
    If i Run Recalculate Assignment Cost Total Budget Cost getting change
    Once Again if i run Global Change i am able to get Correct Budget Cost in activity table any in my S Curve the Problem remain same
    Is there any option to fix it
    Regards
    Anbin