P6 Resource allocation

Lucas lMember for 16 years 7 months
Created
3
2
0
Hello,

I have an enquiry.

Below the situation:

My setting:
Activity Tpe; Resource dependent
Duration Type: Fixed time and fixed unit
Resource Shift:1st 8hrs (0800-1500), 2nd 5hrs (1500-2000)
Resource rates: 1st $20/hr, 2nd $40/h
Resource: Welder

My budgeted manhours is 130 manhrs, which is 10 days duration.Budgeted unit/time =13/hr.

I would expect the labour cost to be 10*20*8 + 10*40*5 = $3600

But Primavera gives me this instead 10*(40+20)/2*13 = $3900

Is this appropiate? Or is there anything wrong with my setting or my understanding of the allocation.

Kindly advice.

Regards
Lucas

3 replies

Oldest first
  1. 0
    Duy Huynh ·
    Hi Lucas,

    For above requirement, you have to create two record in the Resources dictionary for Resource: Welder, Ex:

    Welder: Shift1, effective date xxxxx max unit/time 8h/d, default unit/time 8h/d, price $40.

    Welder 2: Shift2, effective date same as above, max unit/time 5h/d, default unit/time 5h/d, price $20.

    Add both record into which activity you want him to work on.

    That is what best resolve your issue.

    Regards,
    Duy
  2. 0
    Lucas l ·
    Thank Duy Huynh,

    That’s what I did to rectify the situation.

    But I still do not understand why Primvera interpret differently.
  3. 0
    Vladimir Liberzon ·
    It means that if the second shift duration is 8 hours and the work begins at its start then after 5 hours it will stop and wait for the next shift.
    Is it true?
    When the schedule is developing it is not known when activities will start and finish.