P6 Resource allocation
In the Open Standard
Lucas lMember for 16 years 7 months
- Created
- 3
- 2
0
Hello,
I have an enquiry.
Below the situation:
My setting:
Activity Tpe; Resource dependent
Duration Type: Fixed time and fixed unit
Resource Shift:1st 8hrs (0800-1500), 2nd 5hrs (1500-2000)
Resource rates: 1st $20/hr, 2nd $40/h
Resource: Welder
My budgeted manhours is 130 manhrs, which is 10 days duration.Budgeted unit/time =13/hr.
I would expect the labour cost to be 10*20*8 + 10*40*5 = $3600
But Primavera gives me this instead 10*(40+20)/2*13 = $3900
Is this appropiate? Or is there anything wrong with my setting or my understanding of the allocation.
Kindly advice.
Regards
Lucas
I have an enquiry.
Below the situation:
My setting:
Activity Tpe; Resource dependent
Duration Type: Fixed time and fixed unit
Resource Shift:1st 8hrs (0800-1500), 2nd 5hrs (1500-2000)
Resource rates: 1st $20/hr, 2nd $40/h
Resource: Welder
My budgeted manhours is 130 manhrs, which is 10 days duration.Budgeted unit/time =13/hr.
I would expect the labour cost to be 10*20*8 + 10*40*5 = $3600
But Primavera gives me this instead 10*(40+20)/2*13 = $3900
Is this appropiate? Or is there anything wrong with my setting or my understanding of the allocation.
Kindly advice.
Regards
Lucas
3 replies
Oldest firstLog in or join to reply