Resource Curve

Anbin PonnithMember for 17 years 4 months
Created
5
3
0
hai
I assigned Resource Curve for Some Resources, But it is Changing By Total Budgeted Cost
How can i Fix it

Regards
Anbin

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Anbin,

    If I understood you correctly, you assigned Curve to your Activities and not to the Resources.

    As far as I know, if you assigned a curve, only the cost distribution per day/week/month will change according to the assigned Resource Curve but not the Budgeted Cost. Correct me if I am wrong.

    What did you do, can you elaborate further.

    Regards,

    Arnold
  2. 0
    Anbin Ponnith ·
    Dear Sir
    Thanks For ur Reply
    I am working for a Project of 226 Villas.The Client told us to Have only 10 Activities Per Villa.
    1.Substructure
    2.SuperStructure
    3.Roof WaterProofing
    4.Mechanical Hvac
    5.Mechanical Plumbing
    6.Electical & All System
    7.Civil Finishes
    8.Doors & Windows
    9.Specialities,Wood & Plastic
    10.Site Preparation & Boundar Wall
    For Mechanical HVAC,Mechanical Plumbing & Electrical I dont want the Cost to be Distributed Uniformly,So that i Create a new Resource Curve Mechanical HVAC & Modify it
    After that I Select the Activity Mechanical HVAC Click Activity Detail->Resource Tab->Curve
    I Assigned Curve to all Resource Assigned to That Activity
    After Assigning The Curve if i Saw The Budgeted Cost it Getting Changed
    Regard
    Anbin
  3. 0
    Arnold Puy ·
    Hi Anbin,

    Try to check your Duration Type. It should be Fixed Duration & Units. What Resource Curve did you assign?

    Regards,

    Arnold
  4. 0
    Anbin Ponnith ·
    Dear Sir,

    First I created a resource curve for each activity and assigned to all resources regardless of the pay item.But I faced problem in the cost.

    Now I have created separate resource curves for each pay item and assigned and updated the cost comes correct.

    for example,
    for the electrical activity with the pay items,
    1.Conduits
    2.Cables.
    3.Switches & Lights.
    Previously I have assigned a common resource curve for all the pay items above.But the problem was not fixed.
    Now I have created separate resource curve for each pay items & assigned the problem got fixed.

    Is that the procedure.Am I doing correct.


    with Thanks & Regards,

    Anbin Ponnith
  5. 0
    Arnold Puy ·
    Hi Anbin,

    Perhaps the problem is within the creation of your new Resource Curve. I am not quite sure what you have done, but anyway, you solve your own problem. You discover something.

    Regards,

    Arnold