Comparison between Baseline & Actual

Athar HashmiMember for 17 years 6 months
Created
1
3
0
How i can i compare a baseline progress i.e. planned progress with actual progress? Suppose activity A has a planned progress of 100% while it has actual progress of 50%. I want to show a planned progress of 100% in a baseline and actual progress of 50% in activity bar.Please note that i have to enter actual progress (50%) manually.

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Planned progress = Schedule % complete in Primavera. If you want to display the %complete on bar then click the Bar icon. Tick the baseline you want to show (Project BL, Primary BL...etc) While highlighted the selected baseline click the bar level tab. Click add and select where you want it to be display (i.e. Right, Left, Center..etc) then Select Schedule % Complete. Do the same on Actual Bar and select Activity % Complete.

    This should display the % Complete on each bar

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?