Resource orientated schedule
In the Open Standard
Lucas lMember for 16 years 7 months
- Created
- 3
- 1
0
Helo,
I went for Primavera basic course a year ago.
In the course, we are taught to create a resource orientated schedule (resource constraint).
Is that the standard style of resource loading in P6 as it can utilize all resource management function in P6?
The method I am using is more of a unlimited resource schedule. therefore i can’tuse function like resource levelling. If resource is too high, i will do manual levelling.
is that how P6 user use it?
Regards
Lucas
I went for Primavera basic course a year ago.
In the course, we are taught to create a resource orientated schedule (resource constraint).
Is that the standard style of resource loading in P6 as it can utilize all resource management function in P6?
The method I am using is more of a unlimited resource schedule. therefore i can’tuse function like resource levelling. If resource is too high, i will do manual levelling.
is that how P6 user use it?
Regards
Lucas
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?