Activities when imported moves out of WBS

Salman AhmedMember for 16 years 7 months
Created
2
2
0
Hi all,

Request your suggestions on the following situation:

I exported the activities for weightage calculations.When these activites are imported back to P6, they moved from their original WBS to Project level WBS.





2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Salman,

    When exporting files from Primavera, don’t delete the WBS Code column, this is one of the basic unique identifier of activity. If this column remove and import back, all activities will move to Project level WBS and delete the current assignment.
  2. 0
    Salman Ahmed ·
    Thank you Mr.Rodel for your support.

    Salman