Problems in cost loading in Excel sheet

Haresh JayanthMember for 20 years 1 month
Created
2
2
0
1) I want to export P6 files into excel and then cost load in excel sheet. Since WBS headings are not exported in Excel i am finding it difficult to export.....Any solution to export primavera files along with WBS and again to import back..

2) When i export my primavera program i got 5 sheets i.e. RSRC , TASKRSRC,PROJCOST,TASK & USERDATA. But when i tried to load cost under particular resources in Budget column and then import back , my cost are not reflected in P6. it shows "Zero value" . So what is the solution to import cost in Budgeted cost column under particular resource in excel and then import in P6.

Kindly guide on above two issues......

2 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    You can include WBS name when you export data into excel. When you run the export-> spreadsheet-(xls) and reached select template, click modify and select WBS name under general. There is a forum that I explain how to import cost into Primavera using export/import spreadsheet-(xls). I believed either Option 2 or 3 is appropriate for you to use. Instead duration use your estimated cost.

    Duration Percent Complete Post #3
  2. 0
    Ferdinand U. ·
    uncheck cost linked or use global change first