How to show inactive period in an activity which is yet

Jiso ThomasMember for 18 years 7 months
Created
1
4
0
Gents,

We are looking for an option where we will be able to indicate an inactive period in an activity which is yet to start? For example :

Activity Start : 1-May-10
Activity Finish : 1-Sep-10
Data Date : 1-Apr-10
Inactive period required : 15-May-10 to 15-Jun-10

Can we get any help on this?

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Jiso,
    All you need is to assign calendar with inactive period as stated. The bar will still looked straight across from 1-May-10 to 1-Sep-10 but if you set the Bar Necking Settings to Calendar non working time then it will show inactive period.