Reports - Report Scope Column

David BladesMember for 22 years 6 months
Created
3
1
0
When you look at the reports section and the column ’report scope’ I have a drop down option to change the entry from Global to Current Project.

A colleague with the same access as me cannot. Is this something that can be turned on / off???

Thanks in advance

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    David,
    Can you check if he has a global access under User -> Global access Tab-> Global security Profile. He might not have global access privilege.
  2. 0
    David Blades ·
    Hi Rodel

    Yes he has global access. In fact when checking it looks as if he has the same Admin Superuser access as I do.

    A strange one!!!

    Thanks
  3. 0
    Rodel Marasigan ·
    David,
    The best way to check is this process.
    First you need to logoff to Primavera then ask your colleague to logon using your Users Name and password. If the issue still the same then there is a problem with Primavera installed in his machine otherwise something wrong with the profile.