Graphic Report- Bar

Lo GaryMember for 16 years 8 months
Created
3
1
0
Dear,


Could we set the relationship line in the graphic report-bar in P3?


Gary

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Lo,
    Yes you can. Click the relationship lines icon and it will show the line.
  2. 0
    Lo Gary ·
    Dear,

    I mean using the Tool, Graphic Reports, Bar command to set the report. Not the on screen bar chart print out.


    Gary
  3. 0
    Rodel Marasigan ·
    Lo Gary,
    First you post on the wrong section that is why it was interpreted wrongly.
    To answer your question, unfortunately is not possible to set relationship in Graphic Bar printout in P3. I suggest doing same layout on your screen with the relationship line then print.