Graphic reports

Anil GuptaMember for 23 years 2 months
Created
5
2
0
Hi all
I recently started working on P3e/c 3.5.1,I am not able to find tools for generating graphical report as i used to do it in P3. Would any one please let me know how to generate graphical report .
I beleive P3e/c doesn’t seem to have that facility

5 replies

Oldest first
  1. 0
    Mk Tse ·
    Instead of creating the graphic report, the creation is done on display, after that, save the layout as report.
    Display the graphic on screen, goto View -> Home, select the option.
  2. 0
    Forum Guest ·
    thank you
  3. 0
    Forum Guest ·
    Thnks for reply ,i tried the said function and it worked only for indiviual resources..i couldn’t get report for cummulative resources for a particular time period.Hope i am clear.
    E.g i have A,B,C resources working in project , I want to know total how many required in month.
  4. 0
    Alex Wong ·
    You can either use activity usage profile or resource usage profile

    When you use resource usage profile you can select the resource or resources that you want to display in the graph by using the shift/control keys.

    otherwise when you use the activity usage profile you can set up the grahp to display either all lab resource or non lab resource in unit or cost in the activity usage profile options.

    to open the option you need to right click the mouse and select the options from the menu

    Hope that helps

    Cheers

    Alex
  5. 0
    Alex Wong ·
    Or one more possibility is using Primavera Earn Value Pack
    But it will cost you $.

    The only disadvantage of all these is no period performance in P3e ... They (Primavera) said they will introduce the function in the near furture ??