Unlink Gantt chart and Profile view?

Salman AhmedMember for 16 years 7 months
Created
6
5
0
Hi all,

I would like to view the activity table & Gantt chart on the top view, and only profile (graph) in the bottom view (I mean to split the screen in 3 parts instead 4 parts).

Thanks in advance.

6 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Salman,
    In print out yes it possible but not on the screen view.
  2. 0
    Salman Ahmed ·
    Please let me know how to do it in printout.
  3. 0
    Rodel Marasigan ·
    Salman,
    Once the screen view is Gantt chart on Top and Profile at the bottom click Print Preview-> Page Setup-> Option tab.
    Tick Activity Table, All Column (optional), Grid Lines(optional), Gantt chart and Profile
  4. 0
    Salman Ahmed ·
    Thanks for your reply,

    However looking for something else>> when we view Gantt chart on top and profile at bottom, the screen splits into 4 parts >>
    1.top left activity table,
    2.Top right Gantt chart,
    3.Bottom left= "Show usage for..all activities & selected activities option, etc.
    4.Bottom right shows The graph.

    I would like to show ..1 and 2 .>>the top screen which splits the top screen into 2 parts,and only graph in the whole bottom screen without showing point 3 (above mentioned).

    thanks in advance.
  5. 0
    Rodel Marasigan ·
    Salman,
    Like what I have said, for screen view it is not possible. For print out, Print the Activity Table and Gantt chart first as selected on the Options and then Print the Profile separately as one whole page.
  6. 0
    Salman Ahmed ·
    Thanks a lot Mr.Rodel,

    Just wanted to have all that (activity chart, Gantt chart and Profile) in the A0 sheet and paste it in the meeting hall.Now I need to do that separately.