Skip to content

Resource Limits

Haresh JayanthMember for 20 years 1 month
Created
3
3
0
How to Set resource limits in P6 , Which draw the line and shows overallocation...

regards

Haresh

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Enterprise-> Resources-> under Unit & Prices click Add then enter Max Unit/Time
  2. 0
    Rox Lra ·

    Where is the issue when the

    Where is the issue when the limit does not change according to the max units/time?

    Eg. I have set the limit to 10, however when I look at the chart I see is 12

  3. 0
    Rox Lra ·

    Where is the issue when the

    Where is the issue when the limit does not change according to the max units/time?

    Eg. I have set the limit to 10, however when I look at the chart I see is 12

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?