Activity Original Durations & Summary bars
In the Open Standard
Nathaniel AlexanderMember for 23 years 4 months
- Created
- 1
- 2
0
I have just inherited a schedule, from anther company, which I am busy setting a new baseline. I have entered a new activity with a duration of 42 weeks, however when I look at the summary total, under the original duration, it shows me 4 weeks, even though the activity dates and the summary dates, show the same. I have checked the project calendars and the activity calendar, and these appear normal,
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?