Activity Original Durations & Summary bars

Nathaniel AlexanderMember for 23 years 4 months
Created
1
2
0
I have just inherited a schedule, from anther company, which I am busy setting a new baseline. I have entered a new activity with a duration of 42 weeks, however when I look at the summary total, under the original duration, it shows me 4 weeks, even though the activity dates and the summary dates, show the same. I have checked the project calendars and the activity calendar, and these appear normal,

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Nathaniel,
    You need to check further settings. (i.e. Unit Format, Time Format and Hours per time period)
    Select Edit-> Users Preferences-> Time Unit tab
    Under Unit Format-> is it hours or day?
    Under Time Format-> is it hours or day or week?
    Under Hours per time period-> it should match Default Calendar
    Next settings-> What is your Default calendar setting? (i.e. 8hr/d, 10hr/d, 16hr/d or 24hr/d) If using only one calendar Default calendar should match activity calendar and hours per time period.
    Summary band calculate durations using Default Calendar and hours per time period.

Log in or join to reply