Skip to content

Manual update labour unit in resource usage spreadsheet

Lucas lMember for 16 years 7 months
Created
5
2
0
Hi all,

Kindly advice on how to manual update labour unit on the resource usage spreadsheet.

I can only manual the budgeted unit not the remaining unit as well.

Regards
Thanks
Lucas

5 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Hi Lucas,
    Is field remaining early units is present on the spreadsheet? What are your duration type settings? If fixed Units or Fixed Unit/Time then those setting are not updatable in spreadsheet but you can update them on the columns. Fixed Duration and Units or Fixed Duration and Unit/Time are only updatable settings on the spreadsheet.
  2. 0
    Lucas l ·
    Hi,

    yes, it is present in the spreadsheet.

    My duration setting is fixed duration and fixed unit. I check the help section and still can’t solve it.

    I can only make changes to the budgeted units, but not remaining unit and actual unit.

    Kindly advice.

    Regards
    Lucas
  3. 0
    Rodel Marasigan ·
    Lucas,
    You might not have privilege to that field. To set privilege select Admin-> Security Profiles. Tick Project then locates Edit Resource Assignment for Resource Planning and make sure it has tick.
  4. 0
    Lucas l ·
    I have checked and it is ticked.
  5. 0
    Rodel Marasigan ·
    Lucas,
    Last check, are you using roles assignment as resource or resource itself? If roles make sure Edit Roles Assignment for Resource Planning also ticks.

    Make sure that Remaining Early Units is display on the spreadsheet and not Remaining Early Cost.

    It much easier if your profile is set to superadmin (less restriction)

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?