Incorrect float
In the Open Standard
Sophia MMember for 16 years 7 months
- Created
- 4
- 1
0
On the baseline schedule I am working on, I have a milestone with a constrained finish on or before 3/27/14. The Milestone is showing that it is finish on 3/7/14 however it states that there is -50 in float! Why is this happening? I’ve checked everything and I cannot find an incorrect setting!
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?