Total Budgeted Cost & Remaining Cost
In the Open Standard
Arnel LagumbayMember for 18 years 1 month
- Created
- 6
- 2
0
To P6 experts,
Please enlingthened me with this problem I incountered,Iv got this Cost loaded programme which was develope in P3, I imported to P6 succesfully but the problem is when i exported to excel the Cost(Budgeted & Remaining)is not distributed thru its activity full duration.Or some settings that i missed here.
I need your reply guys..thanks
Best regards,
Rnel
Please enlingthened me with this problem I incountered,Iv got this Cost loaded programme which was develope in P3, I imported to P6 succesfully but the problem is when i exported to excel the Cost(Budgeted & Remaining)is not distributed thru its activity full duration.Or some settings that i missed here.
I need your reply guys..thanks
Best regards,
Rnel
6 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?