Does P6 shows date days in text (i.e. Mon, 4/16/10)

Carlos NazarioMember for 17 years 8 months
Created
1
2
0
I was recently asked if there was a way to show dates in the format: Day, mm/dd/yy - ala Microsoft Project.

The closer I got to was to go to Edit > User Preference > Dates... but that format is not one of the options?

For contractors’ three week lookaheads tshoeing the date day in text (Mon, Tues, Wed...) would seem convenient.

Any comments, suggestions?

CN

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Carlos,
    P6 has a function to organize your look ahead schedule by day, week, month, quarter and year using Group and Sort as per sample below.
    P6 2Wk LookAhead