Resource Curve ISSUE in P6

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
3
3
0
Hi Dear Planners,
Is there anybody have an idea how to distribute the resource equally for a period. For eg: I have 10 Engrs. and i would like to use these guys for a period of 3 months.(April , May & June ) Looking at the resource assignments p6 gives 6 for april , 13 may , 11 june, infact it spreading the resource numbers on the basis of the early peak curve but what i need is to spread the resource equally ( 10,10,10) for each month. I have tried with linear curve as well but it doesnt gives me the result the way i need. Is there anyone have any idea how to show the resource assignemnts like this.

I am using p6.1
Regards

3 replies

Oldest first
  1. 0
    Mike Testro ·
    Hi Suresh

    Try putting the resource on a summary bar.

    Best regards

    Mike Testro
  2. 0
    David Blades ·
    Hi Suresh

    I do this on occasion by creating a ’level of effort’ activity for the entire duration; link start to start to your first activity in April and link finish to finish to your last activity in June, both relationships should be under ’predecessor’. Assign your 10 engineers to this level of effort activity and I think this may solve your problem. - Worth a try!

    I hope this helps
  3. 0
    Rodel Marasigan ·
    Suresh,
    You can also use level of effort link from first and last activity of a period if summary task is not possible. (Ex: activities are sitting on different WBS)