Early Start/Finish S-curve vs Baseline S-curve

Cristina BladesMember for 21 years 1 month
Created
2
3
0
Hi,

I have a new project... all the resources are in, the proposed baseline has now been agreed and am trying to run the required S-Curves: Baseline, Early, Late.

As I have the plan open, and showing Start, Finish, Early Start, Early Finish, Late Start, Late Finish columns, I can see a difference between Start and Late Start, however, there is NO difference in the Start and Early Start dates nor the Finish and Early finish dates. Therefore, I assume that the data for my Early and Baseline S-Curves will be exactly the same.

Any help please?

Thank you,
Cristina

2 replies

Oldest first
  1. 0
    Pinan T. ·
    Without update

    Start/Finish date equals Early Dates equals Planned Dates
  2. 0
    Rodel Marasigan ·
    Christina,
    Baseline dates are different from start/ finish date if you have any assigned to current in progress program.