Commencement Date

Moutaz AldeibMember for 22 years 9 months
Created
3
1
0
Dear Planners,

I am reviewing a baseline schedule, the commencement date has TF=2 days?

Regards,

Moutaz

3 replies

Oldest first
  1. 0
    Ali Farhat ·
    so where is the problem?
  2. 0
    Moutaz Aldeib ·
    Dear Ali,

    The problem is that the commencement date should have TF=0 and linked to the critical activities which have TF=0, also in the schedule report I have found "Milestone with invalid relationship"

    Regards
  3. 0
    Roger Booth ·
    Check your calendar. If the calendar is a 5 day week and the commencement date is at a weekend, it will show float equal to the duration until you start work on the Monday

Log in or join to reply