Resource budgeted units being divided?
In the Open Standard
David BladesMember for 22 years 6 months
- Created
- 8
- 4
0
Can anyone tell me what setting is causing this to happen please? I am using task dependent activites, fixed units/time (duration type)
Example. I have an activity with 5 days duration, when I add one resource it’s fine, when I add the second it’s dividing the budgeted units by the number of recources in this case it becomes 2.5 if I were to add a third the budgeted units for each of the 3 recources would become 1.7.
I need to show 5 days for each of the recources.
Thanks in advance
Example. I have an activity with 5 days duration, when I add one resource it’s fine, when I add the second it’s dividing the budgeted units by the number of recources in this case it becomes 2.5 if I were to add a third the budgeted units for each of the 3 recources would become 1.7.
I need to show 5 days for each of the recources.
Thanks in advance
8 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?