To setup the total float

Izam ZakariaMember for 20 years 4 months
Created
1
3
0
Guys,

I’m just wonder if we can change the setting of total float. If right now the 0 will display red bar how do i want to change 10< become critical bar?

Thx

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Izam,
    Tools-> Schedule or (f9) -> Options then enter your parameter to "Total float less than or equal to".

Log in or join to reply