Time Sheets in Resource Usage

Haresh JayanthMember for 20 years 1 month
Created
1
2
0
I know how to assign timesheets, but i want to learn how it is used? Can timesheets be used in a standalone version of P6? How different users are login with timesheets.....Pls explain

1 reply

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    Timesheet is another module in P6. You need to install timesheet module in order to use it. It runs using P6 Web Access and not standalone. Users are login in P6 Web Access and enter their timesheets. Approval of timesheet can be done using P6 PM Module or P6 Web Access.