Resource Codes

Haresh JayanthMember for 20 years 1 month
Created
3
1
0
I have created several resource codes for each resources. And then when i tried to assign resource codes for each resources after inserting a column for resource codes , i am unable to assign the codes.

The resource code column is inactive. How to assign resource codes..

regards,

3 replies

Oldest first
  1. 0
    Rodel Marasigan ·
    Haresh,
    Resource Codes are only for resource. You can assign resource code by selecting Enterprise-> Resource-> Code Tab or Show the created code column under this module (Enterprise-> Resource-> then right click and select the resource code created)
  2. 0
    Haresh Jayanth ·
    Dear Rodel,

    I assigned these resource codes to all resources. But i am unable to understand , how to get benefit from assigning separate codes to all resoruces..

    The concept is not going into my head.....can you help me out, how can i take benefit after assigning resource codes??
  3. 0
    Rodel Marasigan ·
    Haresh,
    Resource Code is used only on Resource Window (Module). It will not available on Activity Window and Project Window and the equivalent is Activity Code for Activity Window or Project Code for Project Window.

    Note:
    Code use for Group & Sorting, filter, show on column.
    Project Code = Project Window, Activity Window but project level and not activity level.

    Resource Code = Resource Window and Resource Level only.

    Activity Code (Global, EPS, Project) = Activity Window, Resource window but activity level only.

Log in or join to reply