Haresh,
You maybe searching a wrong topic. Try good scheduling practice or basic scheduling... etc.
Link below is Proper use of Milestone and Constrain
Scheduling Best Practice
In addition P3.x constrain equivalent to P6
P3 3.x Constraint Type: ------------ P6 PM Constraint Type:
Early Start (start no earlier than) -- Start On or After
Late Start (start no later than) ------ Start On or Before
Early Finish (finish no earlier than) - Finish On or After
Late Finish (finish no later than) ----- Finish On or Before
Start On ---------------------------------- Start On
Expected Finish ------------------------- Expected Finish Date
Mandatory Start ------------------------ Mandatory Start
Mandatory Finish ----------------------- Mandatory Finish
Zero Total Float ------------------------- Not Converted
Zero Free Float -------------------------- As Late As Possible
PMI has a book of Practice Standard for Scheduling which is a good reference link below.
PS Scheduling.
If you are a member of PMI you will have a free access to all ebook that PMI have and you find a lot of good reading materials about Project Management.